9 Jul 23  Project closed by the ANMF/USA Board of Directors.
2 Jul 23  Final Report received from ANMF/Nepal.
1 Feb 23  Report received from ANMF/Nepal.
26 Jan 23  Installation Report received from ANMF/Nepal.
26 Jan 23  Oxygen plant successfully installed.
21 Dec 22  Update from ANMF/Nepal: The oxygen plant room height at Amda Damak is a little small so they are increasing the height. After the construction is complete the installation will be done. Vendor has said that the installation will be completed by next week.
4 Dec 22  Memorandum of Understanding (MOU) signed with Association of Medical Doctors of Asia-Nepal (AMDA-Damak).
17 Nov 22  ANMF/USA Board approved the oxygen plant being allocated to AMDA Hospital - Damak, Jhapa District, Province No. 1.
17 Nov 22  Update received from ANMF/Nepal.
31 Oct 22  $30,000 Sent to ANMF/Nepal for additional transportation costs for 3 Plants.
28 Oct 22  Memorandum of Understanding (MOU) signed with ANMF/Nepal for $30,000 transportation for 3 plants.
20 Sep 22  Update
20 Sep 22  Update received from ANMF/Nepal.
20 Sep 22  Letter received from Lumbine Hospital. Lumbini Hospital has four oxygen plants and has refused to take the oxygen plant.
13 Sep 22  Update received from Medioxy Pvt. Ltd.
21 Aug 22  Waybills (1, 2) of the shipment of the oxygen plants furnished by Flash Freight Logistics who is transporting these plants from France to Birgunj, Nepal. Medioxy will take over from Birgunj to destination hospitals. The shipment sailed from France on 8/6/22 and is expected to reach Singapore in a few days time and finally to Calcutta by 9/16/22. Shipment tracking via E-Schenker.
25 Jul 22  Novair has confirmed that the oxygen plants and refill systems have been loaded on respective containers and have sent the photos as attached in this email. First available date of shipment of these containers via the sea is August 2, 2022.
17 Jul 22  Invoice of payments made for cargo insurance of the plants (1, 2). The insurance for 2 oxygen plants purchased by ANMF from the US is paid separately. The insurance for ANMF's 3rd plant is made together with the rest of the 7 plants from other consortium member organizations. Medioxy made those payments and they will bill ANMF Nepal separately at a later date.
9 Jul 22  Flash Freight Logistics will be doing the sea transportation for free from France to Birgunj (as noted on the MOU (1, 2, 3) signed on 7/8/22). The MOU signed on 3/24/22 had Cargo Packers as the carrier but that has changed as Flash Freight Logistics has agreed to bear the cost of sea transportation. The earliest departure is scheduled on 18-20 July. ETA is August 24th (see Booking Receipt Notice). Any extra cost that ANMF has to bear will be for the travel insurance (which is 0.01% of the total value and Medioxy will be getting the quotes), any taxes during custom clearances, and transportation of plants from Birgunj to respective hospital.
8 Jun 22  Paid MediOxy Receipt received from ANMF/Nepal.
24 Mar 22  MoU - MRN-Medioxy-CPM for transportation of oxygen plants signed.
8 Mar 22  Annex 4 Costing - Medioxy - estimate received.
8 Mar 22  Annex 3 - Packing List of Generators received.
8 Mar 22  Annex 2 - Generators Assigment Plan - Final List - revised received.
8 Mar 22  Annex 1 - Quotation from Cargo Packers for transportation of oxygen plants.
28 Feb 22  Social Welfare Council (SWC) Approval for transportation of oxygen plant received.
26 Feb 22  Update
8 Jan 22  Lumbini Hospital is ready with the infrastructure as confirmed by the Medical Superintendent from the hospital and Bio Medical engineers from Medioxy who had visited the site. The cost of AMC up to 5 years after the 1 years which will be provided free of cost by Medioxy. The cost of spare parts of which they have to assure won’t vary till 10 years. Discounted cost for extra materials provided by Medioxy before installation.
3 Jan 22  Invoice from Flash Freight Logistics Pvt. Ltd.
28 Dec 21  Installation Equipment Quotation received from MediOxy Pvt. Ltd.
22 Dec 21  Update
21 Dec 21  Side Agreement between Mission Rebuild Nepal and Flash Freight Logistics received.
13 Dec 21  Fund Assurance Notice for additonal transportation and handling expenses sent to ANMF/Nepal.
8 Dec 21  Nepal Airlines has issued a Letter of Intent to award the transportation contract to Flash Freight. The carrier needs surplus funds to complete the transportation of the oxygen plants, details about shipping oxygen plants from France to Nepal to be confirmed in the next few days by the carrier.
21 Nov 21  Update on shippping oxygen plants from France to Nepal.
20 Nov 21  Bidding Document for shippping oxygen plants from France to Nepal.
24 Oct 21  Since September 23 approval for additional funding, Nepal Airline Corporation (NAC) put out a 30-day quotation bid for the air-freight(9/20/21- 10/20/21), the formal documentation not yet available. Only one company submitted a bid. Exact gid is unclear, but definitely more than the earlier number. The Ministry of Health is covering this cost and meetings between the three parties are underway but MOH is reluctant to pay this higher price. We hope to know the details in a few more days to come. There is a possibility that the Consortium may have to cover the difference for anything above 275k. Any funds needed will go through ANMF Nepal to the Letter of Credit opened by the vendor, Medoxy. The last resort would be to transport the plant via sea route. The amount of about $15,000 is based on a handling charge in Paris (based on the weight of the freight) and other costs that will be incurred in Nepal based on the breakdown submitted by Mission Rebuild Nepal.
26 Sep 21  Fund Assurance Notice for additonal $5,000 transportation and handling expenses sent to ANMF/Nepal.
23 Sep 21  ANMF/USA Board of Directors approves an additonal $5,000 for transportation and handling expenses.
6 Sep 21  On the oxygen plants from France, the Government of Nepal has formally decided to pay for the airlifting of the plants and has directed Nepal Airlines Corporation (NAC) to identify the freight carrier. NAC is following its procedures to identify a suitable carrier. In the meantime, Mission Rebuild Nepal (MRN) has asked ANMF to consider bearing the costs of cargo handling at the Paris Airport (other members in our consortium will not be funding the cost there). MRN is asking that others in the consortium bear the cost of handling all the plants and transportation in Nepal so that ANMF does not have to bear the cost there. The exact numbers on the costs are not known yet as the freight carrier has not been identified so far.
12 Jul 21  Balance of $51,027.75 transferred to Mission Rebuild Nepal.
7 Jul 21  Plants will be ready July 9th. Plants will be ready to pick up July 12th. Government of Nepal/COVID-19 Crisis Management Center to bear the air freight cost.
24 Jun 21  Quotation for air freight received from Flash Freight Logistics Pvt. Ltd.
9 Jun 21  Update from Novair, France.
7 Jun 21  Oxygen generators should be ready for shipment from France by the first week of July. Medioxy Pvt. Ltd., who will be installing the oxygen plants, has conducting survey of hospitals that will receive the oxygen plants. Medoxy has requested facilities that need improvement for the plant to be installed at the hospital in Butwal.
5 Jun 21  $25,000 donation received from Nepali American Community Center and Neeko Foundation for 21ANMF005 and 21ANMF006.
4 Jun 21  At the direction of the Nepal Ministry of Health and Population, this oxygen plant will be installed at the Lumbini Provincial Hospital in Butwal, Rupandehi.
3 Jun 21  Joint fund raising Memorandum of Understanding with Nepali American Community Center of Fairfax, Virginia and Neeko Foundation of Chantily Virginia signed.
28 May 21  Order Acknowledgement from Novair, France.
21 May 21  $51,765 deposit transferred to Mission Rebuild Nepal.
20 May 21  Memorandum of Understanding with Mission Rebuild Nepal signed.
17 May 21  Project approved by the ANMF/USA Board of Directors.
17 May 21  Oxygen Generator Specifications received from ANMF/Nepal.
17 May 21  Cylinders Filling System Specifications received from ANMF/Nepal.
17 May 21  Medioxy Pvt. Ltd. Proposal received from ANMF/Nepal.
17 May 21  Application received from ANMF/Nepal.